Safety checklist — Glazier / Curtain wall installer
Structural curtain walls, assembly and high-rise installation. Based on Québec's Construction Safety Code (CSTC) and CNESST standards.
Before work
12 items- ✓
PPE worn: hard hat, harness, cut-resistant gloves, glasses, safety shoes
- ✓
Fall protection: guardrails or harness + ≥ 18 kN anchor (CSTC 2.9 / 2.10.15)Critical
ℹ️ CSTC 2.9.1: also no-height cases, 1.2 m on a vehicle, 1.5 m with a load, more than 3 m otherwise. Harness is last resort (2.9.2).
- ✓
Installation plan and sequence reviewed
- ✓
Panels and glazing inspected — no chips, cracks or defects
- ✓
Mechanical or vacuum suction cups tested and charged
- ✓
Weather checked — wind per manufacturer / risk analysis
ℹ️ Sail effect is real; 40 km/h is not a CSTC threshold.
- ✓
Crane or hoist inspected if heavy panels
- ✓
Panel mechanically secured BEFORE releasing suction cup
- ✓
No worker under panel lifting zone (CSTC 3.10.4 (4))Critical
ℹ️ 3.10.4 (4): no load over anyone’s head.
- ✓
Structural fasteners installed per engineer's plan
- ✓
Weather seals installed progressively — no gaps left open
- ✓
Glass offcuts picked up immediately — dedicated container
After work
4 items- ✓
Waterproofing verified — spray test if required
- ✓
Temporary protection applied on glazing
- ✓
Suction cups and tools cleaned and stored
- ✓
Installation report completed (panel numbers, positions)
16 verification items — use this checklist on-site with the app
Use on-site — freePDF reports, history and team management in the app
For information only — this is not legal advice. OK Sécurité is an independent company with no affiliation to the CNESST: we are not mandated, endorsed or certified by it. Completing a checklist here does not by itself establish your compliance — your exact obligations depend on your job site and your prevention program. Where there is any discrepancy, the official text published by Légis Québec or the CNESST prevails.
More checklists — Building Envelope & Roofing
More safety checklists
Risks and prevention — Glazier and curtain wall installer
Curtain-wall erection combines height, heavy loads, and weather. Falls follow CSTC 2.9. Anchor design is Building Code / spec — not a named CSTC+Code pair.
Installers must use harness systems adapted for horizontal travel on the façade. Curtain wall panels must be temporarily secured upon placement to resist wind loads during erection.

Scan to access OK Sécurité
Open the app directly on your phone to complete your safety checklists on-site.
ok-securite.com